Recovering a stalled $85K implementation
I inherited a network infrastructure upgrade that had stalled roughly four months in. Around $85K was committed, delivery had halted, and confidence across the involved groups had eroded.
- Organization
- Hamid General IT Support
- Role
- Project Manager
- Committed
- $85,000
- Duration
- 6 weeks
- Status
- Delivered
The problem
The blocker was not technical. Scope had never been firmly agreed, the original delivery plan no longer reflected reality, and resource and budget assumptions had gone unvalidated.
- Equipment had been ordered before the design was finalized.
- Work had started before requirements and dependencies were validated.
- Client users faced continued disruption while the $85K stayed tied up.
Outcome
- Implementation delivered within six weeks of takeover.
- Stakeholder confidence restored; the project moved from at-risk to delivered.
- Budget preserved, and no further delay added to the schedule.
What I did
- Redefined scope. Established what was actually in and out, and secured agreement from each stakeholder group before restarting work.
- Rebuilt the delivery plan. Replaced the obsolete schedule with a plan built around genuine capacity and real dependencies.
- Resequenced workstreams. Ordered the work so the highest-risk dependencies were confronted first rather than deferred.
- Validated resource and budget assumptions. Confirmed what was truly available instead of inheriting the original estimates.
- Escalated blockers deliberately. Surfaced the issues that would not resolve on their own, with a clear ask attached to each.
- Coordinated vendor inputs. Worked the network vendor and the ISP to secure firm delivery dates and confirmed configuration.
What I took from this
Most stalled projects are not stalled on the work itself. They are stalled because no one has been willing to say out loud that the original plan stopped being true. Naming that early is usually the entire recovery.